Friday, 13 February 2009 17:42 |
|
The project consists of getting an accurate floodplain delineation for Stone Creek. This is accomplished through the submission of a Letter of Map Amendment (LOMR) to FEMA and having it adopted, which amends the current regulatory Floodplain Information Rate Map (FIRM). Contract Documents including the Request for Proposals, Consultant Agreement, and Master Agreement are available under the documents page. These documents contain the detailed project scope. Here is an overview of the project and current progress - Field Surveying of the project site: Completed
- Preliminary Draft Floodplain Delineation: Completed
- Final Draft Floodplain Delineation: Completed
- Stakeholder List and Exhibit Maps: Completed Map and Documents Available Here (Updated 2009/05/27) (Obsolete - Use maps dated 2009/06/12)
- Steering Committee Meetings: Completed
- Stakeholders Group Meeting: June 15, 2009
- Final Floodplain Delineation: Completed Map and Documents Available Here (Updated 2009/06/12)
- LOMR Submission to FEMA: Completed, received by FEMA on August 5, 2009
- FEMA Public Review Process: Decision Document Issued January 15, 2010
- LOMR Adoption and FIRM Revision: June 04, 2010
This project has many properties that may be affected. Two separate teams will be formed to aid the County in this project, as follows: - Steering Committee: The steering committee consists of a small group of active members that will assist the County in the project. See the Steering Committee Page for more information.
- Stakeholders Group: The stakeholders consist of all parties that are along the current regulatory floodplain, the proposed floodplain, any of the stream channels, and any other member from the public that wishes to participate. See the Stakeholders Group Page for more information.
|
|
Last Updated on Tuesday, 19 January 2010 10:56 |
Thank you,
Katherine Howington